Page 19 - Tata Chemical Annual Report_2022-2023
P. 19

Integrated Annual Report 2022-23  01-83  84-192              193-365
               Integrated Report      Statutory Reports       Financial Statements
               Basic Chemistry Business


 Operational and strategic developments – UK   Operational and Strategic Developments – Kenya


 Working closely with customers, the UK operations was able   Way forward  Staying on course  Way forward
 to weather the challenges of high energy cost by modifying its     Ÿ Strengthening UK’s edge in terms of one of the lowest carbon   Kenya business performance during the year remained     Ÿ Improving on Mean Time between Failure (MTBF) and plant
 contracting strategy. This led to all plants operating at full capacity.  footprints in soda ash manufacturing in the EU, Tata Chemicals   healthy both on volumes and realisations. Fulfilling   availability by 10%
 Europe (TCE) UK has developed the first major CCU in the   customer demand across markets was an area of focus     Ÿ Generating cash from operations to support expansion
 During FY 2022-23
 country, a new power plant for salt operation, and an energy-  given supply chain challenges during the year. Strong cash   capex
   Ÿ UK commissioned and fully operationalised a 40 KT carbon   from-waste plant which is expected to be completed by 2026   flows enabled prepayment of all debt.
 capture unit, producing CO  to EIGA (European Industrial   at the Lostock site    Ÿ Production of Pure Ash through solar ponds project in
 2
 Gases Association) standard, for manufacturing of sodium        Q3 FY 2023-24
 bicarbonate    Ÿ Enhancing manufacturing capabilities with new investments     Ÿ Installation and commissioning of 10 MW solar plant
 and continuous improvement in cost efficiencies
   Ÿ Started construction of a new pharmaceutical grade salt
 manufacturing facility and associated warehousing    Ÿ Generating electrical energy at high efficiency from the CHP
 plant as part of the minimisation of the carbon footprint
   Ÿ UK signed an MoU for potential hydrogen supply to the
 Northwich operations    Ÿ Developing strong export capability in high grade and high
 end applications







 Enabling 10% carbon
 footprint reduction


 n 2020-21, TCE constructed the Carbon Capture and   Benefits
 IUtilisation plant (CCU) for capturing CO  from its gas-fired   The project has yielded excellent outcomes.
 2
 Combined Heat and Power plant (CHP) at Winnington,   Commissioned in an exceptionally short period, the
 Northwich. The plant was commissioned in August 2021   CCU has been reducing CO  emissions from the CHP by
 2
 and the first CO  was captured in September 2021. EIGA   40,000 tonnes per annum, which is equivalent to 11% of
 2
 quality approvals were obtained the same month, after   its total emissions.
 which all of the CO  needs of the TCE Sodium Bicarbonate
 2
 (SB) plant at Winnington have been fulfilled from the   We are certain that the project’s success will act as a
 new CCU plant. Initiated in 2018, the project is the first   pathfinder for other CCU projects in the UK, as was
 industrial scale CCU plant in the UK.  intended by BEIS (Business, Energy and Industrial
 Strategy).
 The CO  is liquefied and purified at the CCU to EIGA Food
 2
 and Beverages Grade standards. It is used as a key raw
 material for the manufacturing of high purity SB at the
 Winnington plant.














            Location: Magadi Plant