Page 286 - Tata_Chemicals_yearly-reports-2021-22
P. 286

Integrated Annual Report 2021-22




           4(b). Capital work-in-progress
                                                                                                      ` in crore
                                                                                     Year ended    Year ended
           Particulars
                                                                                 March 31, 2022  March 31, 2021
           Opening carrying value as at April 1                                         1,034.71        787.80
           Additions / adjustments                                                      1,749.34      1,050.91
           Transfer to property, plant and equipment                                   (1,201.14)      (818.54)
           Exchange fluctuations                                                           6.65         14.54
           Closing carrying value as at March 31                                       1,589.56       1,034.71

           Ageing Schedule
           As on March 31, 2022
                                                                                                      ` in crore
           Particulars                     Less than 1 Year  1-2 Years   2-3 Years  More than 3 Years   Total
           Projects in Progress                  1,306.54      138.44       72.74            71.84     1,589.56
           Total                                 1,306.54       138.44      72.74            71.84    1,589.56
           As on March 31, 2021
                                                                                                      ` in crore
           Particulars                     Less than 1 Year  1-2 Years   2-3 Years  More than 3 Years   Total
           Projects in Progress                    788.33      190.78       36.61            18.99     1,034.71
           Total                                   788.33      190.78       36.61           18.99     1,034.71
           Completion Schedule whose completion is overdue:
           Outbreak of Covid-19 pandemic resulted in a few interruptions causing delay in completion of these projects, however these have resumed
           and expected to complete as per table give below:
           As on March 31, 2022
                                                                                                      ` in crore
                                                                         To be completed in
           Particulars
                                                      Less than 1 Year  1-2 Years   2-3 Years  More than 3 Years
           Projects in Progress
           Tata Chemicals Limited  - Project 1                460.74           -           -                -